Phase 6 (Contract 21)    
as of  September 18, 2007

All of Phase 6 has been turned over to the Town. If you live in this area you should have received a letter telling you that you can now connect to the system.

Project Photos
Click here for photos of various parts of Phase 6/Contract 21.

Bid Opening: The bids for Contract 21 (Phase 6) were opened Tuesday, April 29, 2003. The winning bid is from RJV Construction out of Canton, MA. They have done a lot of projects like this for the Boston Sewer and Water Authority.

Phase 6 Design Summary
Approximately 290 homes/businesses served
Approximately 23,000 LF (4.3 miles) of gravity sewer
1 Pumping Station (Hill Street and Main Street)
Approximately 1,400 LF of force main
Approximately 6 Grinder Pumps
Approximately 3,400 LF of water main replacement (bid alternate)
Environmental Impact Report (EIR) waiver granted
No ConCom approvals necessary

Phase 6 Schedule (2003)
Advertise Bids                                   April 4
Plans available to contractors          April 8
Bids received and opened                April 29
Recommendation to Award              May 9
Execute Construction Agreement     May 27
Pre-Construction Conference           June 4
Public Information Meeting               June 19  7:30pm @ TMHS Aud.
Mobilize/Begin Construction             June 23

Phase 6 has been completed.    The Hill St. pumping station is up and running. 284 properties can now connect to the Town's sewer system. Some of the streets received final paving in 2004; the balance will be done in 2005.