Information on Phase 10
Phase 10 (Contracts 32, and 33)     
as of  September 18, 2007

Survey work for Phase 10 is begun. Borings are in process. The company doing the surveys is Survey Mapping Consultants (SMC).

hase 10 streets by contract
This list breaks out Phase 10 into the three contracts that will be used for construction. The contract numbers are 32, and 33.

Phase 10 map
 

Phase 10 Project Summary
Three Construction contracts
Approximately xx,000 LF (xx miles) of gravity sewer
x pumping stations
Approximately x,000 LF of force main
ConCom, DEP (WQC), Army Corps of Engineers approvals required for construction.

Phase 10 Schedule
Field Survey                                
Design Contract #32              
Design Contract #33              

Bidding Contract #32             
Bidding Contract #33               

Phase 10 Contract 32 Schedule:
Advertise Bids                             
Plans available to contractors         
Bids received and opened                  
Recommendation to Award             
Execute Construction Agreement    
Pre-Construction Conference           
Public Information Meeting              
Mobilize/Begin Construction           .  

Phase 10 Contract 33 Schedule:
Advertise Bids                                 
Plans available to contractors          
Bids received and opened                 
Recommendation to Award             
Execute Construction Agreement    
Pre-Construction Conference           
Public Information Meeting              
Mobilize/Begin Construction